How many workers does a data center need?

Somewhere around 2.5 construction workers per megawatt is the middle of the pack. That's the median across the 29 projects on our tracker that report both a peak crew and a size in MW. The biggest single number we have is 10,000 for PORTS Technology Campus.

Treat these as rough. 26 of the 32 crew figures are "construction jobs as reported," which can mean total jobs over the whole build, not people on site on the same day. Each project page links the source so you can see how it was counted.

Do bigger campuses need more workers per MW?

Per megawatt, no. It goes the other way. On our data, projects of 1.5 GW and up have a median of 1.6 workers per MW (11 projects), and smaller ones come in at 4 (18 projects). Big campuses still need the biggest crews. They tend to build in phases, so the whole campus isn't under construction at once.

Which developers need the most workers?

Here's every developer with two or more projects on the tracker and at least one reported crew size. Developers with two or more reported crew sizes have their own page with the project-by-project numbers and sources.

DeveloperProjects trackedWith crew figureLargest reported crewTotal MW listed
Meta767,500 (Hyperion (Richland Parish))10,420
Tract511,000 (Morris Technology Park)10,100
Applied Digital421,000 (Delta Forge 1)1,320
Compass Datacenters411,000 (Hoffman Estates campus (five buildings, former Sears HQ))520
Crusoe415,000 (Stargate I / Lancium Clean Campus (Phases 1-2, 8 buildings))4,000
Google425,500 (Google AI campus (Armstrong County))2,700
Vantage Data Centers414,000 (Lighthouse / Stargate (four data centers, Port Washington))2,670
STACK Infrastructure311,000 (Stafford Technology Campus (four sub-campuses, 19 data centers))1,300
Aligned Data Centers213,000 (Project Phoenix (three facilities))2,540
Hut 8221,900 (Beacon Point (Phases 1-2, Nueces County))1,245
Related Digital222,500 (The Barn / Stargate)1,420
SB Energy2110,000 (PORTS Technology Campus)11,200

Every reported crew size

ProjectDeveloperSizePeak crewWorkers per MW
PORTS Technology CampusPiketon, OHSB Energy10 GW10,0001
Project Star energy campusEncinal, TXRelated Companies + NextEra Energy6.47 GW~8,4001.3
Paducah AI and HPC campus (former DOE enrichment site)Paducah, KYBrookfield1.8 GW8,0004.4
Hyperion (Richland Parish)Holly Ridge, LAMeta5 GW7,5001.5
Joliet Technology CenterJoliet, ILHillwood and PowerHouse Data Centers1.8 GW7,0003.9
Pecos datacenter campusPecos, TXMicrosoft2 GW6,0003
Google AI campus (Armstrong County)Amarillo, TXGoogle—5,500+ on site daily—
Stargate I / Lancium Clean Campus (Phases 1-2, 8 buildings)Abilene, TXCrusoe1.2 GW5,0004.2
Monarch Compute Campus (phase one)Point Pleasant, WVNscale2 GW4,3752.2
Project Jupiter (Doña Ana County)Santa Teresa, NMOracle2.45 GW4,0001.6
El Paso Data CenterEl Paso, TXMeta1 GW4,0004
Lebanon data center campusLebanon, INMeta1 GW4,0004
Lighthouse / Stargate (four data centers, Port Washington)Port Washington, WIVantage Data Centers902 MW4,0004.4
Meta Mason County data center campusMason County, KYMeta2.2 GW4,000+1.8
Project Phoenix (three facilities)Shippingport, PAAligned Data Centers2 GW3,0001.5
Midwest Digital GatewayCanton, OHCorscale312 MW3,0009.6
Project Tembo (formerly Project Jade)Cheyenne, WYGoogle2.7 GW2,5000.9
The Barn / StargateSaline, MIRelated Digital1 GW2,5002.5
Beacon Point (Phases 1-2, Nueces County)Corpus Christi, TXHut 81 GW1,9001.9
Cumberland County data centerFayetteville, NCPRSM Group225 MW1,5006.7
New Albany Data Center / PrometheusNew Albany, OHMeta1 GW1,2001.2
Stafford Technology Campus (four sub-campuses, 19 data centers)Stafford, VASTACK Infrastructure1.1 GW1,0000.9
Morris Technology ParkMorris, ILTract1 GW1,0001
Delta Forge 1Boyce, LAApplied Digital430 MW1,0002.3
River Bend (initial IT capacity)St. Francisville, LAHut 8245 MW1,0004.1
Beaver Dam data centerBeaver Dam, WIMeta220 MW1,0004.5
Delta Forge 2 / Project HighlandsBrookwood, ALApplied Digital210 MW1,0004.8
Hoffman Estates campus (five buildings, former Sears HQ)Hoffman Estates, ILCompass Datacenters200 MW1,0005
Project Red ClayFort Deposit, AL (Lowndes County)Cloverleaf Infrastructure—~1,000—
Hudspeth County data center (Desert Haven)Hudspeth County, TXServerDomes Global (involved)—800—
Cheyenne campus (CoreWeave)Cheyenne, WYRelated Digital420 MW7001.7
Pennsylvania AI data center (initial 100 MW, expandable to 300 MW)Lancaster, PACoreWeave100 MW6006

Canceled projects are left out. Crew figures are as reported by the source on each project page, most of them compiled through Apollo Technical's data center map. Have a better number for one of these? Send it in.