Data center electrician jobs in Texas

We track 30 data center and power megaprojects in Texas: 21 under construction, 8 planned. They're in Lockhart, TX, Lufkin, TX, Pecos, TX, Fort Stockton, TX, Dickens, TX, Albany, TX, Sweetwater, TX, Abilene, TX and 19 more places.

Biggest announced construction crews: Project Star energy campus (~8,400), Pecos datacenter campus (6,000), Google AI campus (Armstrong County) (5,500+ on site daily), Stargate I / Lancium Clean Campus (Phases 1-2, 8 buildings) (5,000).

Public job calls with extra pay right now: STACK Lancaster data center (IBEW 20, Incentive, 2 contractors); DataBank DFW11 (IBEW 20, Incentive, 1 contractor); QTS Lancaster data center (IBEW 20, Incentive, 1 contractor). Source: TrampHereBro, from hall postings.

Every figure links to its source on the project page. Dashes mean not reported.

Each square is a project. 30 shown. Orange: building · Blue: planned · Gray: killed.
ProjectLocationOwner / builderSizeStagePeak workersLocalPer diem / over-scale
STACK Lancaster data centerLancaster, TXSTACK Infrastructure—Building—IBEW 20Incentive (incentive)
DataBank DFW11Red Oak, TXDataBank—Building—IBEW 20Incentive (incentive)
QTS Lancaster data centerLancaster, TXQTS Data Centers—Building—IBEW 20Incentive (incentive)
Helios campus (Dickens County)Dickens, TXGalaxy1.63 GWBuilding———
Frontier (Shackelford County, 10 data centers)Albany, TXVantage Data Centers1.4 GW · $25BBuilding———
Sweetwater 1Sweetwater, TXIREN1.4 GWBuilding———
Stargate I / Lancium Clean Campus (Phases 1-2, 8 buildings)Abilene, TXCrusoe / DPR Construction (lead); Rosendin Electric and Southland (prime contractors)1.2 GWBuilding5,000——
Milam County StargateCameron, TXSB Energy1.2 GWBuilding———
Central Texas campus (three 400 MW phases)San Marcos, TXCloudBurst Data Centers1.2 GW · $14.5BBuilding———
El Paso Data CenterEl Paso, TXMeta / JE Dunn and Hensel Phelps1 GW · $14BBuilding4,000——
Beacon Point (Phases 1-2, Nueces County)Corpus Christi, TXHut 81 GW · $17BBuilding1,900——
Abilene AI factory for Microsoft (adjacent campus, two buildings)Abilene, TXCrusoe900 MWBuilding———
Claude campus (Armstrong County, for Google)Claude, TXCrusoe / DPR Construction, Southland Industries and Rosendin (multi-prime)900 MWBuilding———
Project Caprock (six facilities)Abernathy, TXAligned Data Centers540 MWBuilding———
Thad Hill data center (Bosque County, Phase 1-2 power)Meridian, TXCyrusOne400 MWBuilding———
Freestone Energy Center data center (Phase 1)Fairfield, TXCyrusOne380 MWBuilding———
Barber LakeColorado City, TXCipher Digital300 MWBuilding———
Temple campusTemple, TXRowan Digital Infrastructure300 MW · $700MBuilding———
Project CincoLytle, TXRowan Digital Infrastructure300 MW · $900MBuilding———
Abernathy HPC campus (Fluidstack joint venture)Abernathy, TXFluidstack168 MWBuilding———
Google AI campus (Armstrong County)Amarillo, TXGoogle / Crusoe (developer)—Building5,500+ on site daily——
Project Star energy campusEncinal, TXRelated Companies + NextEra Energy6.47 GW · $22.3BPlanned~8,400——
Caldwell Valley Technology ParkLockhart, TXTract4 GWPlanned———
Champion campus (former Southland Paper Mill)Lufkin, TXAmp Z2.1 GWPlanned———
Pecos datacenter campusPecos, TXMicrosoft2 GWPlanned6,000——
Childress AI data center campusChildress, TXCrusoe1 GWPlanned———
ColchisSan Angelo, TXCipher Digital1 GWPlanned———
Texas Critical Data Centers (TCDC)Odessa, TXNew Era Energy & Digital1 GWPlanned———
Hudspeth County data center (Desert Haven)Hudspeth County, TXServerDomes Global (involved)$15BPlanned800——
Project HorizonFort Stockton, TXPoolside2 GWPaused———

Dashes mean not reported. Worker figures are as announced and may be cumulative, not concurrent. Open a project for its source.