Alabama · Updated Oct 16, 2026
Data center electrician jobs in Alabama
We track 2 data center and power megaprojects in Alabama: 0 under construction, 2 planned. They're in Brookwood, AL, Fort Deposit, AL (Lowndes County).
Biggest announced construction crews: Delta Forge 2 / Project Highlands (1,000), Project Red Clay (~1,000).
No public per diem calls tied to Alabama projects yet. Calls go out through the IBEW or UA local that covers each site.
Every figure links to its source on the project page. Dashes mean not reported.
| Project | Location | Owner / builder | Size | Stage | Peak workers | Local | Per diem / over-scale |
|---|---|---|---|---|---|---|---|
| Delta Forge 2 / Project Highlands | Brookwood, AL | Applied Digital | 210 MW · $3.2B | Planned | 1,000 | — | — |
| Project Red Clay | Fort Deposit, AL (Lowndes County) | Cloverleaf Infrastructure | — | Planned | ~1,000 | — | — |
Dashes mean not reported. Worker figures are as announced and may be cumulative, not concurrent. Open a project for its source.